$5 million bridge preservation project begins along I-77

15 bridges over I-77 and I-277 will be “preserved” in future months; NCDOT hopes to extend their life and avoid more expensive repairs

mhurley@charlotteobserver.comJune 25, 2012 

  • Bridge work The following bridges will be preserved along I-77: Nations Ford Road; N.C. 49 (South Tryon Street); Clanton Road; Remount Road; Fifth Street; Cindy Lane; Sunset Road; N.C. 24 (W.T. Harris Boulevard); Mount Holly-Huntersville Road; Gilead Road; Stumptown Road; and Sam Furr Road. The following bridges will be preserved on I-277: Inner and outer loops of John Belk Freeway over I-77.

The N.C. Department of Transportation will begin a 14-month project Monday to preserve 15 area bridges over Interstate 77. The project is targeting bridges in good shape that would be far more expensive to repair or replace in future years if preventative measure are not taken now, said Garland Haywood, the department’s division bridge engineer for the Charlotte area.

“It’s really to prolong the life of the bridges,” he said. “These are bridges that were built anywhere from 1968 to 1973 ... they’re in good shape now, but (after the preservation project) we’re going to get at least 20 more years out of these bridges without any maintenance.”

The maintenance project will cost $5 million for all the bridges and is expected to be completed by the end of August 2013. According to Haywood, the cost of replacing any of these bridges, if they were allowed to deteriorate to an irreparable state, would be several times the cost of preservation.

“Any one of these bridges could cost us $800,000 to maybe $1.5 million to replace,” Haywood said. “This is basically upkeep ... we want to do this to save money.”

The contractor chosen by the state DOT, HRI Bridge Co. of State College, Pa., will work on the bridges one at a time over the course of the projects. HRI Bridge will start with the John Belk Freeway bridges over I-77, spending roughly two to four weeks on each bridge as they work north. The last bridge to be preserved will be the Stumptown Road crossing in Huntersville.

Nearly all the construction will be performed at night, Haywood said, with crews working on one lane at a time to prevent closures. The only roads that will close temporarily and require detours will be the entrance and exit ramps at John Belk Freeway and N.C. 49/South Tryon Street.

While each bridge requires a slightly different approach, the most common preservation technique is a deck overlay. This requires crews to remove the existing deck and apply a latex modified concrete overlay. Some bridges will also have bearing plates replaced or cracks sealed in their concrete support columns.

“They’ve each got different work depending on the bridge,” Haywood said. “Basically, we want to preserve what we have. They’re in good shape now and we need to try and hold on to that infrastructure.”

The Herald is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.